CO129-307 - Governor Sir Blake - 1901 [10-12] — Page 368

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All AI Reviewed

41080

Pe 25 NOV 01

Public Works Office.

365

COPY

No.746.

Hong-Kong, 24th August, 1901.

Sir,

I have the honour to forward you herewith the Estimates for Public Works Extraordinary for 1902. The following are some comments with regard to them.

GOVERNOR'S PEAK RESIDENCE. The estimated cost for this work has been increased from $105,000 to $140,000. I have already given the details of this item in No.1762 of 1901 and since then water-closets and drainage have been added. I hope the sum stated will be found adequate to cover the cost.

NO.7, POLICE STATION. The estimated cost in this case has been increased from $24,000 to $31,000. The contract which has been let for the buildings amounts to $27,319.28 without allowance for water or gas service, &c.

PRAYA RECLAMATION. The sum asked for is the balance of the Government Contribution towards the work.

PRAYA RECLAMATION GOVERNMENT PIERS. The estimated cost for this item has been increased from $215,000 to $300,000. The actual amount expended to 30th June last was $237,357.22 and there still remained at that date some outstanding liabilities on Blake Pier and a pier to be constructed.

The Honourable

THE COLONIAL SECRETARY.

Edit History

2026-06-01 02:25:27 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
41080 Pe 25 NOV 01 Public Works Office. 365 COPY No.746. Hong-Kong, 24th August, 1901. Sir, I have the honour to forward you herewith the Estimates for Public Works Extraordinary for 1902. The following are some comments with regard to them. GOVERNOR'S PEAK RESIDENCE. The estimated cost for this work has been increased from $105,000 to $140,000. I have already given the details of this item in No.1762 of 1901 and since then water-closets and drainage have been added. I hope the sum stated will be found adequate to cover the cost. NO.7, POLICE STATION. The estimated cost in this case has been increased from $24,000 to $31,000. The contract which has been let for the buildings amounts to $27,319.28 without allowance for water or gas service, &c. PRAYA RECLAMATION. The sum asked for is the balance of the Government Contribution towards the work. PRAYA RECLAMATION GOVERNMENT PIERS. The estimated cost for this item has been increased from $215,000 to $300,000. The actual amount expended to 30th June last was $237,357.22 and there still remained at that date some outstanding liabilities on Blake Pier and a pier to be constructed. The Honourable THE COLONIAL SECRETARY.
Baseline (Original)
41080 Pe 25 NOV 01 Public Works Office. 365 COPY No.746. Hong-Kong, 24th. August,1901. sir, I have the honour to forward you herewith the Estimates for Public Works Extraordinary for 1902. The follow- ing are some comments with regard to them. GOVERNOR'S PEAK RESIDENCE. The estimated cost for this work has been increased from $105,000 to $140,000. I have already given the details of this item in 0.3.0.1762 of 1901 and since then water-closets and drainage have been added. I hope the sum stated will be found adequate to cover the cost. NO.7,POLICE STATION. The estimated cost in this case has been increased from $24,000 to $31,000. The contract which has been let for the buildings amounts to $27,319.28 without allowance for water or gas service,&c. PRAYA RECLAMATION. The sum asked for is the balance of the Government Contribution towards the work. PRAYA RECLAMATION GOVERNMENT PIERS, The esti- mated cost for this item has been increased from $215,000 to $300,000. The actual amount expended to 30th. June last was $237,357,22 and there still remained at that date some out- standing liabilities on Blake Pier and a pier to be construct- The Honourable THE COLONIAL SECRETARY. ed
2026-06-01 02:25:27 · Baseline
View content

41080

Pe 25 NOV 01

Public Works Office.

365

COPY

No.746.

Hong-Kong, 24th. August,1901.

sir,

I have the honour to forward you herewith the

Estimates for Public Works Extraordinary for 1902. The follow-

ing are some comments with regard to them.

GOVERNOR'S PEAK RESIDENCE. The estimated cost

for this work has been increased from $105,000 to $140,000.

I have already given the details of this item in 0.3.0.1762

of 1901 and since then water-closets and drainage have been

added. I hope the sum stated will be found adequate to cover

the cost.

NO.7,POLICE STATION. The estimated cost in this

case has been increased from $24,000 to $31,000. The contract

which has been let for the buildings amounts to $27,319.28

without allowance for water or gas service,&c.

PRAYA RECLAMATION. The sum asked for is the

balance of the Government Contribution towards the work.

PRAYA RECLAMATION GOVERNMENT PIERS, The esti-

mated cost for this item has been increased from $215,000 to

$300,000. The actual amount expended to 30th. June last was

$237,357,22 and there still remained at that date some out-

standing liabilities on Blake Pier and a pier to be construct- The Honourable

THE COLONIAL SECRETARY.

ed

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.